June Return 2005 Public Domain

Northumbrian & Essex & Suffolk

Boards Overview, Table B
Sewerage Service - Key Outputs and Service Delivery


Description Units 1997-98 1998-99 1999-00 2000-01 2001-02 2002-03 2003-04 2004-05
KEY OUTPUTS AND SERVICE DELIVERY
DG5 - PROPERTIES AT RISK OF FLOODING
1 Removed by company action nr 23 32 34 33 57
2 % of total domestic properties subject to internal sewage flooding % 0.02 0.02 0.02 0.02 0.01 0.03 0.03 0.02
DELIVERING THE QUALITY ENHANCEMENT PROGRAMME
3 Sewerage improvements: % of satisfactory intermittent discharges % 98.18 96.48 89.55 82.54 72.50 74.11 75.93
4 Sewerage improvements: number of intermittent discharges improved nr 12 47 22 70 76
5 STW Improvements: Population equivalent served by improved STWs 000s 307.70 3,382.00 79.90 171.21 278.71
6 STW Improvements: Number of enhanced sewage treatment works nr 7 14 28 19 36
MAINTAINING SERVICEABILITY TO CUSTOMERS
7 Sewer collapses per 1,000km nr 10.0 5.0 6.0 7.0 6.0 5.0 1.7 5.0
8 Nr of pollution incidents at CSOs and sewers (categories 1 to 3) nr 177 98 88 135 145 131 181 191
9 Percentage of sewage treatment works failing numeric consents % 0.50 0.50 0.70 0.70 1.16 0.93 2.12 0.94
10 % equivalent population served by non compliant works failing LUT consents % 1.70 0.00 0.70 0.00 0.00 1.50 1.09 0.00
11 Properties flooded in the year (overloaded sewers) nr 192 160 89 114 34 141 274 115